ANNOUNCEMENT | 26 MAY 2026 | ASX: E25
UPDATE ON US HPMSM PROJECT EXECUTION PLAN
HIGHLIGHTS
• Review of HPMSM Project Execution Plan underway to optimise development strategy in response
to evolving EV market conditions and emerging battery chemistries.
• Strong ongoing engagement with strategic partners for the Louisiana HPMSM facility.
• Constructive engagement with General Motors & Stellantis to renegotiate contracts.
• Element 25 near term focus is the Butcherbird Expansion Project (BBX) delivery.
Element 25 Limited (E25, Element 25 or Company) (ASX: E25; OTCQX: ELMTF) advises it is
undertaking a review of its Project Execution Plan for the Company’s proposed production of high purity
manganese sulphate monohydrate (HPMSM) in the United States. The review is in response to evolving
electric vehicle (EV) demands in the United States (US) and globally, alongside ongoing assessment of
emerging EV battery chemistries and the Company’s near-term focus on delivering the planned
expansion of the Butcherbird Manganese Project.
Element 25 is working to commercialise innovative proprietary technology to produce battery-grade
HPMSM for use in EV battery manufacturing. Its first HPMSM refinery, proposed for Louisiana, USA,
would produce raw material for the US EV market.
The Company and the HPMSM project has support from key strategic partners in global automakers
General Motors LLC (GM) and Stellantis N.V. (Stellantis), as well as Louisiana Economic Development
(LED), and the U.S. Department of Energy (DoE), with a grant for US$166 million (A$268M) in project
funding under DoE’s Battery Materials Processing Grant Program1
. Element 25 continues to receive
strong support from its key strategic partners.
Changes to the HPMSM project schedule has resulted in certain Conditions Precedent (CPs) with
respect to project delivery timelines under the existing GM agreements not being satisfied. An updated
agreement requires negotiation and the parties are constructively engaged and maintain a collaborative
approach to review and revise commercial arrangements as appropriate. The Company is in parallel
discussions with Stellantis regarding their respective agreements.
In collaboration with its partners and stakeholders, Element 25 is actively repositioning its HPMSM
project to align with current market conditions, the long-term projections of the EV market and demands
for HPMSM, while also incorporating the development sequencing of its Butcherbird Expansion Project
(BBX) in Western Australia.
1
E25 ASX Announcement dated 20 January 2025
26 MAY 2026 | ASX: E25 2
Element 25 Managing Director Justin Brown said:
“Element 25 is taking decisive steps to ensure our HPMSM
strategy fits with the rapidly evolving global EV and battery
materials market. The landscape has shifted materially over the
past 12 months, and it is essential that our strategy reflects current
demand signals as well as the emerging chemistry mix being
adopted by major equipment manufacturers across the EV and
other battery markets.”
EVOLVING BATTERY CHEMISTRY
Lithium manganese-rich (LMR) and lithium-manganese-iron-phosphate (LMFP) battery chemistries are
expected to materially increase global manganese demand due to their significantly higher manganese
intensity relative to conventional battery technologies.
LMR and LMFP batteries are characterised by a significantly higher
proportion of manganese relative to conventional cathode
chemistries, substituting more expensive materials such as nickel
and cobalt.
LMR battery cells use around 50% to 70% manganese, increasing
the required manganese by up to 10X compared to high nickel
ternary chemistries. This increased manganese content not only
reduces overall battery costs but also enhances energy density and
performance2
.
LMR batteries can deliver energy density comparable to conventional nickel-rich chemistries, while
achieving higher energy density than lithium iron phosphate (LFP) batteries. In addition, the stable
cathode structure of LMR materials enhances thermal stability and safety performance, further
supporting their suitability for large-scale EV adoption3
.
Major automotive manufacturers, including GM and Ford, are actively advancing LMR battery
technologies in these areas, as well as supply chain stability, highlighting the growing commercial
momentum behind manganese-rich chemistries4,5
.
As LMR and LMFP adoption scales across the electric vehicle sector, demand for high purity
manganese products, particularly HPMSM, is expected to grow. This trend reinforces manganese’s
emerging role as a critical and strategic raw material within the global EV battery supply chain.
2
https://news.gm.com/home.detail.html/Pages/topic/us/en/2025/may/0513-LMR-batteries-outlook-EV-market.html?pubDate=20250518
3
https://inside.lgensol.com/en/2025/11/a-better-life-with-batteries-lithium-manganese-rich-batteries-with-high-energy-density-safety-and-cost-competitiveness/
4
https://news.gm.com/home.detail.html/Pages/news/us/en/2025/may/0513-GM-LG-Energy-Solution-pioneer-LMR-battery-cell-technology.html
5
https://www.spglobal.com/automotive-insights/en/blogs/2025/07/lmr-battery-technology-the-next-rival-to-lfp
26 MAY 2026 | ASX: E25 3
ELEMENT 25’S INTEGRATED DEVELOPMENT STRATEGY
The Company is expanding its Butcherbird operations to a
nominal 1.1Mtpa manganese concentrate production, based
on an updated January 2025 Feasibility Study6
and an Ore
Reserve of 101.4Mt at 10.4% Mn (10.54Mt contained
manganese)7
, supporting an 18+ year Life of Mine (LOM) at
the planned throughput rate.
Butcherbird’s expanded manganese ore output is intended to
supply the Company’s planned HPMSM facility in Louisiana, as
well as supplying customers in the established ferroalloys
(steel) market.
Element 25’s integrated development strategy, linking its Butcherbird Expansion Project with its
proposed US-based HPMSM processing facility, places the Company in a strong position to capitalise on
these emerging market dynamics and support the evolving requirements of global EV manufacturers.
In addition to the specific terms of the GM and Stellantis
contracts, the review of the USA HPMSM Project will include
aspects such as site selection and associated contracts,
completion of project finance, construction timelines, target
commissioning dates, and updating grant agreements with the
US Department of Energy to align with the revised project plan.
Element 25 will provide a further update to the market upon
completion of the HPMSM Project Execution Plan review.
ABOUT ELEMENT 25
Element 25 is an ASX-listed company (ASX: E25) that operates the world-class 100%-owned
Butcherbird Manganese Project in Western Australia and is currently undertaking activities to
recommence production at approximately 1.1Mtpa8
of medium-grade high silica manganese ore for use
in traditional and new energy markets.
Company information, ASX announcements, investor presentations, corporate videos, and other investor
material in the Company’s projects can be viewed at: www.element25.com.au.
This announcement is authorised for market release by Element 25 Limited’s Board of Directors.
Justin Brown Media Inquiries:
Managing Director
Email: admin@e25.com.au
Phone: +61 (8) 6375 2525
Nathan Ryan
Email: nathan.ryan@nwrcommunications.com.au
Phone: +61 (0) 420 582 887
6
E25 ASX Announcement dated 22 January 2025
7
E25 ASX Announcement dated 22 January 2025
8
E25 ASX Announcement dated 22 January 2025
26 MAY 2026 | ASX: E25 4
Competent Persons Statement
The Company confirms that in the case of Production Targets, all material assumptions underpinning the production target, or the forecast
financial information derived from a production target, in the market announcement dated 22 January 2025 continue to apply and have not
material changed. All estimates or Mineral Resources or Ore Reserves underpinning the production target have been prepared by a competent
person or persons s in accordance with the requirements of the JORC Code, Appendix 5A.
The Company confirms that in the case of Mineral Resource or Ore Reserves, all material assumptions and technical parameters underpinning
the estimates in the market announcements dated 29 October 2024 and 22 January 2025 continue to apply and have not materially changed.
The Company confirms that it is not aware of any new information or data that materially affects information included in previous
announcements, and all material assumptions and technical parameters underpinning the estimates continue to apply and have not materially
changed.
Investor Relations Disclaimer
Certain Statements included in this announcement are forward-looking statements concerning Element 25 Limited and its subsidiaries (E25)
and its operations, economic performance, financial condition, plans and expectations. Without limiting the foregoing, statements including the
words “believes”, “anticipates”, “plans”, “expects”, “could”, “potential”, “should” and similar expressions are also forward-looking statements.
All forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual
events or results to differ from those expressed or implied, including, without limitation, business integration risks; uncertainty of production,
development plans and cost estimates, commodity price fluctuations; political or economic instability and regulatory changes; currency
fluctuations, the state of the capital markets, uncertainty in the measurement of mineral reserves and resource estimates, E25’s ability to attract
and retain qualified personnel and management, potential labour unrest, reclamation and closure requirements for mineral properties;
unpredictable risks and hazards related to the development and operation of a mine or mineral or mineral deposit or mineral processing facility
that are beyond E25’s control, the availability of capital to fund all of the Company’s projects and other risks and uncertainties.
You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. E25 cannot assure you
that actual events, performance or results will be consistent with these forward-looking statements, and management’s assumptions may prove
to be incorrect. E25’s forward-looking statements reflect current expectations regarding future events and operating performance and speak
only as of the date hereof and E25 does not assume any obligation to update forward-looking statements if circumstances or management’s
beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place
undue reliance on forward-looking statements.