Butcherbird Expansion Enters Main Construction Phase
Released
Released
Announcement PDF
Element 25 Limited
Level 1, Building B, Garden Office Park,
355 Scarborough Beach Road,
Osborne Park 6017, Western Australia, Australia
ABN: 46 119 711 929
T: +61 8 6375 2525
E: admin@e25.com.au
W: element25.com.au
ANNOUNCEMENT | 28 October 2026 | ASX: E25
ELEMENT 25 PROGRESSES TO MAIN CONSTRUCTION PHASE
AT BUTCHERBIRD EXPANSION PROJECT, WA
HIGHLIGHTS
• Early site works nearing completion at the Butcherbird Expansion Project in preparation for the
planned main construction phase.
• Works completed include site clearing, bulk earthworks and preparation of the planned process
plant, run-of-mine and non-process infrastructure as construction of process water storage pond
and pipelines.
• Existing administration facilities have been relocated and new transportable offices and
amenities installed, together with supporting power, communications, potable water and
wastewater services.
• The program has established essential infrastructure and construction-ready areas for
subsequent processing plant construction and commissioning.
• Tender process for main construction contract – SP1 (CSMP) and E&I construction contract
SP2 (E&I) work package approaching finalisation and award.
• Significant progress achieved toward financial close of Northern Australia Infrastructure Facility
(NAIF) AU$50 million financing package. Major contracts signed include:
• Mining Services Agreement.
• Ore Haulage Agreement.
• Engineering Services Agreement.
• Offtake Agreement.
• Kumarina Camp Lease Agreement.
• Detailed engineering is substantially complete; engineering resources now tasked with
construction support and oversight.
• Main Construction – SP2 is on scheduled to commence Q4 2026, with completion of SP2
scheduled for Q1 2027.
• Operational readiness program significantly advanced as project moves closer to operations.
Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to advise early site
works are materially complete at its Butcherbird Expansion Project (BBX) in preparation for process
plant construction and commissioning in accordance with the BBX project execution plan (PEP).
28 October 2026 | ASX: E25
2
Element 25 Managing Director Justin Brown said: “Our Butcherbird Expansion Project
continues to advance strongly across all major work fronts. We have secured important
commercial contracts, advanced financing activities, progressed engineering and procurement
programs, and significantly strengthened both our construction and operational readiness
capability.
A particularly important milestone is the completion of the SP1 early works package by Qetra.
These works establish the critical infrastructure required to support major construction activities
and represent the first significant site-based execution contract associated with the expansion
project.
In parallel, we have continued significant investment in operational readiness, ensuring that the
people, systems, governance structures and operating procedures required for long-term success
are being developed well ahead of commissioning."
Figure 1: Aerial overview of early works activities at the Butcherbird Project – September 2026.
Figure 2: Aerial overview of early works activities at the Butcherbird Project – October 2026.
28 October 2026 | ASX: E25
3
The SP1 work program establishes critical project infrastructure and construction-ready areas
necessary to support the subsequent development of the expanded 1.1Mtpa manganese concentrate
operation1
. Completion of these activities will enable the transition to the main construction phase,
being SP2 and SP3 and support the planned recommencement of production at Butcherbird.
PROJECT PROGRESS DASHBOARD
Programs Work Packages
NAIF Contractual Close Process Complete Procurement Program On Track
Financial Model & Funding
Package
Complete Long Lead Equipment
Procurement
Orders Placed
Due Diligence Program Advanced Financial Close In Progress
Agreements & Contract Awards Plans & Frameworks
Mining Services Agreement Complete Detailed Engineering Complete
Ore Haulage Agreement Complete Operational Readiness
Framework
Complete
Detailed Engineering (IFC) Complete Pit-to-Port Operating Model Complete
Offtake Agreement Complete Organisational Design Complete
Kumarina Camp Lease Complete Workforce Planning Complete
Early Site-Works Contract Complete Recruitment Planning Advanced
Port Services Agreement Advanced Training & Competency
Framework
Advanced
Power Supply Agreement Advanced Mine Safety Management
System (Construction)
Complete
Main Construction (CSMP) Award Mine Safety Management
System (Operations)
Advanced
E&I Construction Tender Operational Systems Planning Advanced
Construction Mobilisation
Planning
Advanced Statutory Appointments
Planning
Advanced
1
E25 ASX Announcement dated 22 January 2025
28 October 2026 | ASX: E25
4
SP1 WORK PACKAGE SCOPE SUMMARY
The early works program, being SP1, was structured to provide critical project infrastructure and
establish construction-ready areas for subsequent major contracts associated with the construction of
the BBX processing plant and supporting facilities.
Early works focused on establishing the site infrastructure and prepared work areas required for the
main plant construction program, is scheduled for completion Q4, 2026.
Scope of Early Works
Key activities completed include:
• Site clearing, grubbing and bulk earthworks to establish construction platforms for the expanded
processing plant, run-of-mine infrastructure and supporting facilities.
• Construction and commissioning of a new process water pond, including associated water
supply, pumping and pipeline infrastructure required to support construction and future
operations.
• Relocation and reinstatement of existing water services, including bore field pipeline
connections and standpipe facilities.
• Relocation of existing administration and support facilities and installation of new offices,
amenities and other non-process infrastructure.
• Installation of preliminary site services, including power, communications, potable water,
wastewater, roads and drainage infrastructure.
• Decommissioning and rehabilitation of the existing process water pond following successful
commissioning of the new facility.
Detailed engineering activities are now materially complete with issued for construction (IFC)
packages issues across civil, structural, mechanical, piping, electrical and instrumentation packages
(CSMPE&I). Altris Engineering has transitioned into a procurement and construction support role,
providing continuity of personnel through the construction and commissioning phases.
Engineering priority work streams include:
Final issued-for-construction documentation. Construction support.
Vendor data integration. Procurement interfaces.
Commissioning preparation activities.
PROCUREMENT
Procurement activities continue to advance across the expansion project.
All major equipment packages are awarded, ordered and progressing through manufacturing in
preparation for delivery in line with the construction plan. Procurement activities remain focused on
schedule-critical and long-lead items required to support the overall project schedule.
28 October 2026 | ASX: E25
5
Procurement priority work streams include:
Structural steel. Procurement interfaces.
Mechanical equipment packages. Critical spares and commissioning inventory.
Electrical infrastructure and MCCs. Instrumentation and control systems.
Process plant equipment. Conveying systems.
CONSTRUCTION READINESS
Construction readiness remains a major focus as the Company prepares for mobilisation to
immediately follow financial close under the lender financing contract.
To support delivery in accordance with the overall project plan, the construction packages have been
broken into multiple phases, SP1 (Early Works), SP2 (CSMP) and SP3 (E&I).
The SP1 package was awarded to Qetra and is now materially complete. SP1 represents a critical
enabling works package that establishes the site infrastructure required to support the main
construction phase of the project.
The SP1 package is designed to prepare the project site ahead of commencement of the larger SP2
process plant construction package.
The SP1 scope includes:
Site establishment infrastructure. Access and logistics infrastructure.
Construction laydown areas. Early civil works.
Temporary construction facilities. Construction support infrastructure.
Utilities and site services. Camp and accommodation interfaces.
SP2 comprises the primary process plant and associated infrastructure construction programme and
represents the largest construction package within the expansion project.
SP3 comprising the Electrical and Instrumentation construction and installation is the final phase of
the project prior to hand over to the operational readiness team. This short phase is currently in the
final tendering and scheduling phase and expected to run concurrently with SP2.
The completion of SP1 marks an important transition from project development into physical site
execution and establishes the foundation required for efficient delivery of major construction activities.
Additional construction readiness activities completed or underway include:
Construction execution planning. Statutory appointment planning.
Site mobilisation planning. Site logistics planning.
Contractor interface management. Camp mobilisation planning.
Construction safety planning.
28 October 2026 | ASX: E25
6
OPERATIONAL READINESS
Operational readiness has become a major
strategic focus for the Company and represents a
significant de-risking initiative ahead of project
commissioning.
Element 25 has continued development of a
comprehensive Pit-to-Port operating framework
covering mining, processing, logistics,
maintenance, inventory management, laboratory
services, safety, environmental management,
business systems and operational governance.
This aims to ensure the project transitions
seamlessly from construction into stable and
sustainable operations.
Key achievements include:
• Development of an integrated Pit-to-Port operating architecture.
• Establishment of authoritative operating plans across business functions.
• Workforce planning and organisational design development.
• Recruitment planning for operational and statutory roles.
• Development of training and competency programs.
• Maintenance and asset management readiness planning.
• Supply chain and inventory readiness planning.
• Production accounting and reporting framework development.
• Safety management and governance planning.
• Site access, accommodation and travel management planning.
Dedicated operational readiness workstreams are progressing across recruitment, training, systems
implementation, governance, maintenance readiness, supply chain readiness and statutory
compliance.
PROJECT FINANCE
The Company continues to work closely with the Northern Australia Infrastructure Facility (NAIF),
legal advisers, technical consultants and commercial counterparties to complete the remaining
conditions precedent associated with financial close.
Substantial progress has been made across legal, technical, financial, environmental and commercial
due diligence activities. Concurrent advancement of the Company's contracting strategy has
significantly reduced project execution risk and increased certainty around project delivery, operating
costs and future operational performance.
Following multiple key project agreements now completed, the Company has entered the final phase
of activities required to achieve financial close.
28 October 2026 | ASX: E25
7
Financial Close Contract Status
The table below summarises the principal commercial agreements supporting financial close.
Commercial Agreement Status
Mining Services Agreement Complete
Ore Haulage Services Agreement Complete
Engineering Services Agreement Complete
Offtake Agreement Complete
Kumarina Camp Lease Agreement Complete
Port Services Agreement Advanced
SP1 Early Works Contract (Qetra) Complete
SP2 Process Plant Construction Contract (CSMP) Award Process
SP3 E&I Plant Construction Contract (E&I) Tender
The remaining agreements are progressing through final negotiation and execution and are expected
to be completed as part of the broader financial close work program.
ABOUT ELEMENT 25
Element 25 is an ASX-listed company (ASX: E25) that operates the world-class 100%-owned
Butcherbird Manganese Project in Western Australia and is currently undertaking activities to
recommence production at approximately 1.1Mtpa of medium-grade high silica manganese ore2
for
use in traditional and new energy markets.
E25 is also commercialising innovative proprietary technology to produce battery-grade high-purity
manganese sulphate monohydrate (HPMSM) for use in battery manufacturing. The Company is
planning its first HPMSM refinery in Louisiana USA to produce raw material for the US market, with a
grant for US$166 million (AU$268 million) in project funding from the U.S. Department of Energy
(DoE) under the Battery Materials Processing Grant (MESC) Programme3
.
An anticipated strategic shift towards lithium manganese rich (LMR) battery chemistries over high
nickel formulations will materially increase demand for HPMSM, with automakers looking to adopt this
technology after extensive research. Automakers have announced plans to introduce LMR batteries to
improve safety, energy density, and reduce costs. LMR battery cells use around to 50-70%
manganese increasing the required manganese by up to 10X compared to high nickel ternary
chemistries.
2
E25 ASX Announcement dated 22 January 2025
3
E25 ASX Announcement dated 7 July 2026
28 October 2026 | ASX: E25
8
Company information, ASX announcements, investor presentations, corporate videos, and other
investor material in the Company’s projects can be viewed at: www.element25.com.au.
This announcement is authorised for market release by Element 25 Limited’s Board of Directors.
Justin Brown Media Inquiries:
Managing Director
Email: admin@e25.com.au
Phone: +61 (8) 6375 2525
Nathan Ryan
Email: nathan.ryan@nwrcommunications.com.au
Phone: +61 (0) 420 582 887
Competent Persons Statement
The Company confirms that in the case of Production Targets, all material assumptions underpinning the production target, or the forecast
financial information derived from a production target, in the market announcement dated 22 January 2025 continue to apply and have not
material changed. All estimates or Mineral Resources or Ore Reserves underpinning the production target have been prepared by a
competent person or persons s in accordance with the requirements of the JORC Code, Appendix 5A.
The Company confirms that in the case of Mineral Resource or Ore Reserves, all material assumptions and technical parameters
underpinning the estimates in the market announcements dated 29 October 2024 and 22 January 2025 continue to apply and have not
materially changed.
The Company confirms that it is not aware of any new information or data that materially affects information included in previous
announcements, and all material assumptions and technical parameters underpinning the estimates continue to apply and have not
materially changed.
Investor Relations Disclaimer
Certain Statements included in this announcement are forward-looking statements concerning Element 25 Limited and its subsidiaries (E25)
and its operations, economic performance, financial condition, plans and expectations. Without limiting the foregoing, statements including
the words “believes”, “anticipates”, “plans”, “expects”, “could”, “potential”, “should” and similar expressions are also forward-looking
statements.
All forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual
events or results to differ from those expressed or implied, including, without limitation, business integration risks; uncertainty of production,
development plans and cost estimates, commodity price fluctuations; political or economic instability and regulatory changes; currency
fluctuations, the state of the capital markets, uncertainty in the measurement of mineral reserves and resource estimates, E25’s ability to
attract and retain qualified personnel and management, potential labour unrest, reclamation and closure requirements for mineral properties;
unpredictable risks and hazards related to the development and operation of a mine or mineral or mineral deposit or mineral processing
facility that are beyond E25’s control, the availability of capital to fund all of the Company’s projects and other risks and uncertainties.
You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. E25 cannot assure you
that actual events, performance or results will be consistent with these forward-looking statements, and management’s assumptions may
prove to be incorrect. E25’s forward-looking statements reflect current expectations regarding future events and operating performance and
speak only as of the date hereof and E25 does not assume any obligation to update forward-looking statements if circumstances or
management’s beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above,
you should not place undue reliance on forward-looking statements.