Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
27 OCTOBER 2023 | ASX: E25
QUARTERLY REPORT
Highlights
Battery-Grade High Purity Manganese (HPMSM) progress
•
General Motors completes due diligence and accepts the E25 Feasibility Study (FS) achieving a key milestone.
•
Front-end Engineering and Design (FEED) completed to optimise HPMSM plant design for preferred Louisiana site.
•
Detailed project execution schedule finalised with mechanical completion on track for 2025 target.
•
Detailed engineering activities commenced and ongoing.
•
Preferred site offers potential advantages including over-the-fence supply of sulphuric acid, steam and other key inputs.
•
Site assessments including cultural, environmental and geotechnical surveys completed, with no issues or concerns.
•
Site lease in advanced negotiations, remains subject to agreement on acceptable sulphuric acid pricing terms.
•
Project execution plan advancing in line with project development timelines outlined in the FS.
•
All contractual milestones under the General Motors LLC (GM) and Stellantis N.V. (Stellantis) offtake and funding packages on track.
•
Final approvals for Louisiana state government subsidy package received.
Butcherbird Manganese Operations, WA
•
Butcherbird production strategy adjusted to focus on utilising existing stockpiles for processing, thereby reducing mining expenditure.
•
Finished product to be stored onsite until required for shipment, resulting in reduced haulage cashflows..
•
Revised operational strategy to reduce site costs pending ore price recovery.
•
Workforce optimisation to reduce costs and improve cashflows.
•
Strategy allows operational readiness to be maintained to ramp production as manganese prices recover.
•
Strategic operations team to focus on expansion feasibility study.
Butcherbird Expansion Planning
•
General Manager (Manganese Ore Business) Gideon van Wyk leading and managing the expansion.
•
Most key FS activities completed including process flow design, equipment selection, mass balance, vendor quotations and
scheduling.
•
Production expansion FS targeted for release in coming quarter pending completion of remaining tasks.
Corporate
•
Element 25 joins the OTCQX market in the United States, upgrading from the Pink® market, trading under the symbol “ELMTF”.
•
E25 presents to Clean Energy Metals Investor Conference.
Element 25 Limited
Level 1, Building B, Garden Office Park,
355 Scarborough Beach Road,
Osborne Park WA 6017
ABN: 46 119 711 929
T: +61 8 6375 2525
E: admin@e25.com.au
W: element25.com.au
HPMSM Project Execution
In April 2023, E25 published the detailed FS for the construction of an integrated battery grade high purity manganese sulphate
facility in Louisiana, USA (Facility) to produce battery grade high purity manganese sulphate monohydrate (HPMSM) 1. HPMSM
is a critical raw material used in the construction of lithium-ion battery cathode precursor materials to power the electrification
of the global vehicle fleet. The HPMSM produced in Louisiana will be used in the manufacture of electric vehicle Pre-Cathode
Active Materials (pCAM).
The Facility will utilise concentrate produced from E25’s existing operations at the Butcherbird Manganese Mine which
currently exports high silica manganese concentrate for use in the steel industry. The concentrate produced at Butcherbird is
uniquely suited for conversion to HPMSM using Element 25’s proprietary process, which has a number of unique advantages
over existing processes used in China.
The process is energy efficient, eliminates the use of certain toxic reagents, reduces energy and reagent consumption, and
importantly, produces waste residues on forms that can be placed in other industrial processes, targeting a zero waste
footprint. The Butcherbird concentrate, coupled with the E25 process positions the Company as an industry leader in the
production of ethical, secure, low carbon, long term supply of HPMSM to the global electric vehicle (EV) industry.
The Facility is supported by key offtake and funding agreements in place with General Motors LLC (GM) and Stellantis N.V.
(Stellantis), which are contributing a combined US$115M in project funding through a combination of equity, pre-payment and
senior debt alongside offtake for approximately 65% of the planned HPMSM production from the first production train.
Subsequent to the FS release, E25 has continued to engage local engineering firms CSRS Inc (CSRS) and FIDES (a CSRS
subsidiary) as owner’s engineers and CDI Engineering Solutions (CDI) and Universal Plant Services (UPS) as design and
construction engineers to continue to refine the engineering and design of the facility prior to commencement of construction
targeted for first half 2024. Key focus areas include:
•
Front end Engineering and Design (FEED).
•
Site assessments and permitting.
•
Inbound and outbound logistics and reagent supply.
•
Project financing.
Engineering/Procurement Services
CSRS, FIDES, CDI and UPS are experienced local engineering contractors in Louisiana with a track record of chemical plant
design and construction in the Louisiana region. Subsequent to the publication of the FS, E25 engaged CDI (with the support of
UPS) to execute front end engineering and design (FEED) for the Project. The FEED programme began in early May 2023 and is
now complete.
1
Reference: Company ASX release dated 12 April 2023.
El
t 25 Li it d
2
Figure 1. Plant design based on updated detailed engineering 3D model developed as part of FEED studies.
Figure 2. Render showing plant internal layout – product packaging and distribution warehouse.
The FEED work programme included engineering conducted to a greater level of rigor and detail compared to a Feasibility
Study. It is an important engineering phase which provides additional engineering and cost estimation detail as a project
transitions from conceptual design to an Engineering, Procurement and Construction (EPC) contract.
The FEED study typically precedes a final investment decision phase of a large project such as E25’s planned HPMSM facility in
Louisiana. The scope of the study covers engineering disciplines including:
El
Site layout optimisation.
Civil and Structural design and layout.
t 25 Li it d
3
Process flow diagrams.
Process and instrumentation diagrams.
Electrical design.
Piping and mechanical design.
Material take-offs to inform cost estimation activities.
E25 has commissioned FIDES, CDI and UPS to undertake the next phase of detailed engineering and design which will advance
the project through to FID and commencement of construction targeted for 2024.
Engineering Subcontractors
CSRS Inc
CSRS is an engineering and architectural services firm with six (6) offices across the Gulf South and 250 employees. The services
provided include industry site selection, governmental advisory, environmental permitting, surveying, site engineering design,
port advisory, hydraulics & hydrology, and stormwater solutions.
CSRS is engaged as the strategic consultant to E25 for aspects specific to the development of the project in Louisiana.
Fides Consulting
Fides Consulting is a subsidiary of CSRS providing program and project management owner support services, including
conceptual design and front-end project planning for renewable fuels, clean energy, chemical and petro-chemical projects.
Fides has engineers of all disciplines to manage and oversee the engineering design and technical aspects of projects.
FIDES is engaged as the Owner’s Engineer for E25.
CDI Engineering
CDI is a full-service Engineering, Procurement, and Construction Management firm serving the energy and chemical industries
in the USA. CDI has nine (9) offices in the USA with a major office in Baton Rouge, LA. In business for over 70 years, providing
services to a range of clients from major energy producers to pilot plant developers.
CDI is responsible for the Engineering and Procurement scope of the EPC Joint Venture with UPS.
Universal Plant Services
Established in 1968, UPS is a leading provider of project construction and maintenance services for small to large capital
projects. These services include fabrication, welding, piping, mechanical, structural, electrical, instrumentation, and inspection
services, among others. UPS contracts combined to deliver a revenue of US$453M in 2021.
UPS is responsible for the Construction scope of the EPC Joint Venture with CDI.
El
t 25 Li it d
4
Supply Agreements
Negotiations have commenced with regard to utility, service and reagent suppliers, including natural gas, power and sulphuric
acid. All are at an appropriate stage in alignment with the project schedule. Finalisation of these contracts will only occur once
the proposed site for the construction of the Facility is formally selected, which remains dependent on finalisation of the LED
incentives package and various co-dependent commercial discussions with the landowner.
Contractual arrangements with local suppliers, or nearby facilities are also being negotiated to utilise their existing
infrastructure to provide key process and logistical inputs to the project including:
•
Sulphuric Acid;
•
Steam;
•
Raw water;
•
Water treatment;
•
Construction materials offloading; and
•
Manganese ore offloading.
The potential to source this infrastructure and related services without needing to build dedicated infrastructure is an
important part of the execution strategy to minimise capital costs.
Site Selection Programmes
Cultural Survey
APA, a local archaeological consultancy was engaged under contract with CSRS, to undertake a Phase I cultural resources
survey for the proposed Facility site in Ascension Parish, Louisiana. The Phase I survey was performed in March 2023. The
purpose of this study was to determine if any prehistoric or historic properties exist within the limits of the project area, and if
so, to document and assess each based on the National Register of Historic Places.
The proposed site has been historically used for agricultural purposes and no archaeological sites, historic areas, historic
structures, or cultural material were found as a result of this survey. APA recommends that the project area be cleared of any
cultural resource concerns.
Wetland Delineation Survey
The purpose of this study was to determine which areas should be considered jurisdictional wetlands and waters when
submitted for U.S. Army Corps of Engineers (USACE) permit for approval. Jurisdictional Wetlands and Waters require a permit
from the USACE before any construction can begin in those designated areas.
All critical surveys were completed with minor potential wetlands areas covering approximately 400m2 identified for follow up
with USACE.
El
t 25 Li it d
5
Geotechnical, Boundary & Topographical Surveys
Completed in April 2023, the survey data is used to validate the
piling and foundation capacities for the site and to establish the
topographical datum for the site. This data is further utilised for the
digital 3D model for the project design basis.
The programme comprised the drilling and sampling of test
boreholes and performing cone penetration tests (CPTs) to
evaluate subsurface stratigraphy and groundwater conditions at
the project site. Deliverables from the programme based on
geotechnical and analytical laboratory tests on the recovered soil
Figure 1: Cone penetration test (CPT) track mounted rig.
samples included a detailed report detailing findings including
existing project site conditions, subsurface soil and groundwater
conditions including: design recommendations including;
•
Shallow foundation systems;
•
Deep foundation systems;
•
Ground storage tanks;
•
Rigid, flexible and aggregate-surfaced pavement systems;
•
Heavy haul roads (HHRs) and aggregate-surfaced laydown areas;
•
Heavy crane lifts and/or transloading sites; and
•
Site and subbase preparation, excavation considerations,
Figure 2: Soil test borehole drilling rig.
dewatering and groundwater control, fill and backfill placement, compaction requirements, foundation installation and quality
control testing, monitoring and inspection guidelines.
Government / Local Industry Engagement
The E25 HPMSM facility will bring significant economic benefits to a local
community through the creation of new direct and indirect jobs during
construction and operations. Louisiana Economic Development (LED) estimates the project would result in an additional 408
new indirect jobs, for approximately 628 new jobs in the Capital Region.
As a result of this ongoing engagement, the state of Louisiana has offered Element 25 a competitive incentives package to
support a final decision in Louisiana. The incentives include property tax abatements of up to 80% for up to 10 years at parish
level and abatements in state property and sales taxes as well as wage subsidies and utility headworks contributions from the
state. The final part of the incentives package consists of an in-kind recruitment and training package offered by Louisiana
Economic Development. The incentive is provided on the understanding that a minimum number of quality jobs will be
created, and a certain level of investment will be made in industrial buildings.
El
t 25 Li it d
6
The Company has also applied for the state’s Quality Jobs and Industrial Tax Exemption Programs (ITEP) 2 which includes local
government tax abatements and state-based incentives. The application has now passed the local parish’s finance committee,
school board and council meetings unanimously and has been recommended for approval by the Louisiana Government and
ultimately the Governor. The agreement is expected to be issued for execution in coming weeks.
Project Financing
Financing for the proposed Louisiana Facility is cornerstoned by binding commitments for US$115M from offtake partners
General Motors and Stellantis 3. The strategy to complete the funding stack includes a number of parallel processes including
the investigation of funding under the Department of Energy ATVM loan programme, conventional senior debt alongside the
GM senior loan facility of US$85M, strategic investment from a third offtake partner as well as project level equity partners. The
Company is progressing these various discussions in parallel and will provide a more detailed update as soon as further details
are available. Notably, Stellantis has completed the first tranche investment of US$15M in equity and is now the Company’s
largest shareholder with a 10.2% shareholding 4.
Pilot-Scale Metallurgical Test Programme
A final pilot-scale process verification test programme for the E25 flowsheet was completed at
Veolia HPD’s North America facility. The programme utilised the purified leach solution (PLS)
previously produced and processed it through the Veolia pilot scale crystalliser facility using
optimised conditions established in previous test programme(s).
The programme was successful, producing HPMSM well within the required specifications for
battery applications and well inside the E25 Standard Specification which is the quality stipulated
in the agreements with both Stellantis and GM.
The results have exceeded expectations and confirmed the E25 process as being able to deliver
into existing requirements but also to offer opportunities to supply higher purity product options
into the future as battery technology develops and higher purities are required.
The programme also yielded significant quantities of HPMSM which has been packaged and
stored in suitable conditions before being dispatched to E25’s existing offtake partners as well as
potential future offtake and funding partners to assist in ongoing discussions.
Figure 3: E25 HPMSM Sample.
2
https://www.opportunitylouisiana.gov/led-news/news-releases/news/2023/04/12/element-25-proposes-ev-battery-materials-facility-in-ascension-parish
3
Refer ASX releases dated 9 January 2023 and 26 June 2023.
4
Reference: Company ASX release dated 11 July 2023.
El
t 25 Li it d
7
General Motors accepts E25 Feasibility Study
In June 2023, Element 25 and General Motors Co. (NYSE: GM) announced binding agreements for E25 to supply up to 32,500
metric tons of manganese sulphate annually, which will support GM’s annual production of more than 1 million EVs in North
America 5.
Under the agreements, GM will provide E25 with a US$85M loan to partially fund the construction of a new facility in Louisiana,
USA, for production of battery-grade manganese sulphate – a key component in lithium-ion battery cathodes – starting in
2025 6 (Facility). At the Facility, E25 will produce manganese sulphate by processing manganese concentrate from its mining
operations in Western Australia. It is expected to be the first facility of its kind in the US 7.
During the quarter, GM completed due diligence and accepted E25’s HPMSM Feasibility Study as a key milestone in the
agreements. Remaining conditions include completion of product validation, securing the balance of the required project
financing, finalising project permitting and execution of contracts in relation to the preferred plant site in Louisiana, USA. E25
will provide updates as this progresses towards finalisation.
5
Reference: Company ASX Release dated 26 June 2023
6
Reference: Company ASX Release dated 12 April 2023.
7
Reference: Company ASX Release dated 30 September 2022.
El
t 25 Li it d
8
Butcherbird Operations
Production
Due to macroeconomic factors weighing
Production Summary
on demand from Chinese steel makers,
Category
Unit
Opening Product Inventory
t
32,710
26,489
24,654
Mined Ore
t
280,037
252,486
311,385
Concentrate Production
t
41,101
59,350
62,277
Product Sales
t
42,001
47,271
62,418
Closing Product Stockpiles
t
31,810
32,710
26,489
Shipping Cost
t
$
15.00
$
18.00
$
14.90
CIF China 44% Benchmark Price
USD
$
4.37
$
4.98
$
6.00
manganese ore prices are currently at
cyclical lows 8. Whilst prices have flattened,
they remain depressed, and the timing of a
recovery remains uncertain.
Whilst demand and prices are expected to
recover in the medium term, E25 is
restructuring manganese production at
Mar-23
$20.00
Shipping Cost
$10.00
environment.
This will preserve available cash and allow
the strategic operations team to focus on
Jun-23
Key Metrics
Butcherbird to reduce ore production and
costs to align with the lower ore price
Sep-23
$8.00
Manganese Price
$6.00
$4.00
the downstream processing plant
engineering and potential plant expansion
activities whilst maintaining operational readiness and logistics and supply chains to capitalise when prices recover.
The immediate strategy at site involves the ceasing of increasing mined stockpiles and the processing of available mined
stockpiles providing approximately six months of plant feed at budgeted production targets. Finished product will be
stockpiled at site deferring haulage to port which is the largest operating cost pertaining to the Butcherbird operations.
Haulage will resume on a campaign basis when manganese pricing returns to normal levels.
Further cost reductions will be targeted through optimising labour resourcing and adjusting to the operational schedule with a
focus on improved maintenance and plant uptime during reduced operational windows.
Production output is expected to continue at current levels despite reduced resourcing and operational windows, with
increased maintenance supporting improved throughput rates aiming for an overall reduction in operating costs per tonne.
During this period of reduced production resourcing, the operations team will focus on improving operating systems and
operational disciplines to provide a foundation for the expansion of the team as the potential plant expansion is evaluated.
8
https://www.fastmarkets.com/commodity-price/manganese-ore-index-37-mn-cif-tianjin-mb-mno-0003
El
t 25 Li it d
9
Production Expansion Plans
Engineering works on the proposed plant expansion to a nominal
1Mtpa of concentrate production are nearing completion, with
activities during the quarter comprising the core activities
Activity
Status
Process flow design
Complete
Mass balance
Complete
outlined in Table 1.
Equipment selection
Complete
Remaining activities include plant layout, civils design, water
Vendor quotations for principle
mechanical equipment
Complete
Electrical load list - complete.
Complete
Water supply/aquifer pump tests
Complete
Process flow design
Complete
and scheduling for the expansion to be implemented subject to a
Electrical and instrumentation
In Progress
final investment decision by the Element 25 Board.
Detailed project schedule
In Progress
Target outcomes of the revised plant design using dense media
Layout and civil engineering
In Progress
separation instead of ore sorting include increased recoveries and
Finalise capital and operating cost
estimates
In Progress
Project approvals
In Progress
Feasibility report
In Progress
balance and detailed project schedule and budget. Once the final
information has been received and compiled in the coming
quarter, a feasibility study will be released outlining detailed costs
grade. Coupled with reduced unit operating costs drive by
economies of scale and improved production volumes are
expected to significantly improve project economics over the
Table 1. Expansion planning activities
current pilot processing facility.
Corporate
E25 joins the US OTCQX market
During the quarter, E25 began trading on the OTCQX market in the United States under the symbol “ELMTF”, upgrading from
the Pink® market.
OTC Markets Group Inc. (OTCQX: OTCM) operates regulated markets for trading 12,000 U.S. and international securities. Its
data-driven disclosure standards form the foundation of three public markets: OTCQX® Best Market, OTCQB® Venture Market
and Pink® Open Market.
Upgrading to the OTCQX Market is an important step for companies seeking to provide transparent trading for their U.S.
investors. For companies listed on a qualified international exchange, streamlined market standards enable them to utilize
their home market reporting to make their information available in the U.S.
To qualify for OTCQX, companies must meet high financial standards, follow best practice corporate governance and
demonstrate compliance with applicable securities laws.
B. Riley Securities, Inc. acted as the company’s OTCQX sponsor.
El
t 25 Li it d
10
About Element 25
Element 25 is an ASX listed company (ASX: E25) operating the world class 100%-owned Butcherbird Manganese Project in
Western Australia and developing battery grade high purity manganese sulphate monohydrate (HPMSM) products for
traditional and new energy markets. It aims to become an industry leading, world class, low-carbon battery materials
manufacturer.
Company information, ASX announcements, investor presentations, corporate videos, and other investor material in the
Company’s projects can be viewed at: www.element25.com.au.
Justin Brown
Media Inquiries:
Managing Director
Nathan Ryan
Email: admin@e25.com.au
Email: nathan.ryan@nwrcommunications.com.au
Phone: +61 (8) 6375 2525
Phone: +61 (0) 420 582 887
ASX Additional Information
The ASX Appendix 5B quarterly report covering the three-month period ending 30 September 2023 is attached and lodged with
this report. In accordance with ASX Listing Rule 5.3.5, payments to related parties of the Company and their associates during
the quarter totalled $130,000 comprising salary, directors’ fees, consulting fees and superannuation. In accordance with ASX
Listing Rule 5.3.1, payments relating to Mining Exploration totalled $16,000.
Competent Persons Statement
The company confirms that in the case of estimates of Mineral Resource or Ore Reserves, all material assumptions and technical parameters underpinning the
estimates in the market announcements dated 17 April 2019 and 19 May 2020 continue to apply and have not materially changed. The company confirms that
the form and context in which the competent person’s findings are presented has not been materially modified from the original market announcements.
The information in this report that relates to Exploration Results and Exploration Targets is based on information compiled by Mr Justin Brown who is a
member of the Australasian Institute of Mining and Metallurgy. At the time that the Exploration Results and Exploration Targets were compiled, Mr Brown was
an employee of Element 25 Limited. Mr Brown is a geologist and has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Brown consents to the inclusion of this information in the form and context in which
it appears in this report.
This announcement is authorised for market release by Element 25 Limited’s Board of Directors.
Forward Looking Statements
This announcement may include forward-looking statements. These forward-looking statements are based on Element 25’s expectations and beliefs
concerning future events. Such forward-looking statements concern Element 25’s anticipated results and progress of its operations in future periods, planned
exploration and, if warranted, development of its properties and plans related to its business and other matters that may occur in the future. These statements
relate to analyses and other information that are based on forecasts of future results, estimates of amounts not yet determinable and assumptions of
management. All statements contained herein that are not clearly historical in nature are forward-looking, and the words “anticipate,” “believe,” “expect,”
“estimate,” “may,” “might,” “will,” “could,” “can,” “shall,” “should,” “would,” “leading,” “objective,” “intend,” “contemplate,” “design,” “predict,” “potential,”
“plan,” “target” and similar expressions are generally intended to identify forward-looking statements.
Forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors which could cause actual events or results to
differ from those expressed or implied by the forward-looking statements. Forward-looking statements in this release include, but are not limited to,
statements with respect to risks related to:
El
t 25 Li it d
11
•
Element 25’s operations being further disrupted and Element 25’s financial results being adversely affected by public health threats, including any
renewed coronavirus pandemic;
•
Element 25’s limited operating history in the HPMSM industry;
•
Completing required permitting, zoning and re-zoning activities required to commence processing operations for Project;
•
Element 25’s ability to achieve and maintain profitability and to develop positive cash flows from Element 25’s mining and processing activities;
•
Investment risk and operational costs associated with Element 25’s exploration activities;
•
Element 25’s ability to enter into and deliver products under supply agreements;
•
The pace of adoption and cost of developing electric transportation and storage technologies dependent upon lithium batteries;
•
Element 25’s ability to access capital and the financial markets;
•
Recruiting, training and developing employees;
•
Compliance with government regulations;
•
Environmental liabilities and reclamation costs;
•
Estimates of and volatility in HPMSM prices or demand for HPMSM;
•
Element 25’s share price and trading volume volatility; and
•
Element 25’s failure to successfully execute Element 25’s growth strategy, including any delays in Element 25’s planned future growth.
All forward-looking statements reflect Element 25’s beliefs and assumptions based on information available at the time the assumption was made. These
forward-looking statements are not based on historical facts but rather on management’s expectations regarding future activities, results of operations,
performance, future capital and other expenditures, including the amount, nature and sources of funding thereof, competitive advantages, business prospects
and opportunities. By its nature, forward-looking information involves numerous assumptions, inherent risks and uncertainties, both general and specific,
known and unknown, that contribute to the possibility that the predictions, forecasts, projections or other forward-looking statements will not occur. Although
Element 25 have attempted to identify important factors that could cause actual results to differ materially from those described in forward-looking
statements, there may be other factors that cause results not to be as anticipated, estimated or intended. Should one or more of these risks or uncertainties
materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those anticipated, believed, estimated, or expected.
Element 25 cautions readers not to place undue reliance on any such forward looking statements, which speak only as of the date made. Except as otherwise
required by the securities laws of Australia, Element 25 disclaims any obligation to subsequently revise any forward-looking statements to reflect events or
circumstances after the date of such statements or to reflect the occurrence of anticipated or unanticipated events. Element 25 qualifies all the forward
looking statements contained in this release by the foregoing cautionary statements.
El
t 25 Li it d
12
ASX Additional Information for Quarterly Report to 30 September 2023
Tenement
Location
Interest at
reference
beginning of
quarter
Acquired/
Disposed
Interest at end
of quarter
The mining
tenements held at
the end of the
quarter and their
E20/659
Eelya Hill WA
10%
N/A
10%
E46/1366
Black Hill WA
100%
N/A
100%
E52/15