Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) announces it will immediately commence detailed design,
planning and procurement for expansion of manganese ore production at its 100%-owned Butcherbird Mine in WA in line with
the expansion Feasibility Study (FS) released earlier in January 20241.
Expansion of the processing facility at Butcherbird aligns with E25’s commissioning target date for its planned battery grade
high purity manganese sulphate monohydrate (HPMSM) project to be built in Louisiana, USA in partnership with General
Motors LLC and Stellantis NV2.
Activities over the next three months will focus on detailed engineering and design, project financing and finalising the
required permitting to support the commencement of construction in line with the project schedule.
In parallel with expansion activities, the Company will suspend Butcherbird’s current production operations, aiming to reduce
operational cash outflows and re-focus resources and available cash on implementing the expansion plan outlined in the FS.
Recent weak manganese prices support this decision.
E25 Managing Director Justin Brown said: “Expanding the scale of operations at Butcherbird beyond our Stage 1 pilot
plant has always been a part of our growth plans and given the outstanding metrics reported in the updated Feasibility
Study released earlier this month, this is the ideal time to implement those plans to ensure we can increase production
ahead of our Louisiana HPMSM facility commencing operation.
Given the current manganese price environment coupled with high interest rates and inflation, we will suspend current
operations at Butcherbird to conserve resources and use available cash to achieve this goal. We understand this is a difficult
decision for our employees, contractors and suppliers and not one we have made lightly, but it is intended to help E25
better position itself to reach its longer term goals. ”
The current schedule anticipates operations to recommence in approximately 11 months, following project financing being
secured, when E25 will increase annual production to 1.1 million tonnes per annum of manganese oxide concentrate. Further
detail and an updated schedule will be provided at conclusion of front-end engineering and design (FEED) which has now
commenced.
1
Reference: Company ASX Release dated 23 January 2024.
2
Reference: Company ASX Releases dated 9 January 2023 and 26 June 2023
Element 25 Limited
Level 1, Building B, Garden Office Park,
355 Scarborough Beach Road,
Osborne Park WA 6017
ABN: 46 119 711 929
T: +61 8 6375 2525
E: admin@e25.com.au
W: element25.com.au
ABOUT ELEMENT 25
Element 25 is an ASX-listed company (ASX: E25) operating the world class 100%-owned Butcherbird Manganese Project in
Western Australia and developing battery grade high purity manganese sulphate monohydrate (HPMSM) products for
traditional and new energy markets. It aims to become an industry leading, world class, low-carbon battery materials
manufacturer.
Company information, ASX announcements, investor presentations, corporate videos, and other investor material in the
Company’s projects can be viewed at: www.element25.com.au.
Justin Brown
Media Inquiries:
Managing Director
Nathan Ryan
Email: admin@e25.com.au
Email: nathan.ryan@nwrcommunications.com.au
Phone: +61 (8) 6375 2525
Phone: +61 (0) 420 582 887
Element 25 Limited
Share your feedback
Discover