ANNOUNCEMENT | 30 January 2025 | ASX: E25
DECEMBER 2024 QUARTERLY REPORT
QUARTERLY HIGHLIGHTS
Butcherbird Manganese Operations
• Updated Feasibility Study (FS) completed for
Butcherbird expansion based on 1.1Mtpa manganese
concentrate production 1.
• FS delivers compelling economics with an NPV8 of
AU$561M and an IRR of 96% on estimated CAPEX of
AU$64.8M.
• Expansion case will establish Butcherbird as a low-cost
manganese operator (US$2.86/dmtu C1 cost).
• Butcherbird Measured and Indicated Resources increased
142% to 130Mt at 10.23% Mn 2.
• Total Mineral Resource Estimate increased by 6% to
274Mt @ 10% Mn 3.
• Ore Reserve increased 107% to 101.4Mt at 10.4% Mn for 10.54Mt contained manganese.
• Ore Reserve confirms Butcherbird’s robust, >18-year LOM operation at 1.1Mt annual
production rate, in line with E25’s strategic plan1.
• Ore Reserve and mine plan based on only two of eight manganese deposits at Butcherbird.
• Butcherbird Expansion Project Mining Proposal and Mine Closure Plan approved.
Battery Grade High Purity Manganese (HPMSM) - Louisiana, USA
Subsequent to quarter end:
• E25’s planned HPMSM facility in Louisiana formally awarded US$166 million (AU$268 million) 4
grant from the U.S. Department of Energy (DoE).
• Grant is in addition to US$115 million (AU$185 million) in project funding secured from GM and
Stellantis. 5
E25 ASX Announcement dated 22 January 2025.
E25 ASX Announcement dated 29 October 2024.
3
E25 ASX Announcement dated 22 January 2025.
4
USD:AUD conversion rate 0.62. Reference: www.xe.com
5
E25 ASX Announcement dated 21 February 2023.
1
2
Element 25 Limited
Level 1, Building B, Garden Office Park,
355 Scarborough Beach Road,
Osborne Park 6017, Western Australia, Australia
ABN: 46 119 711 929
T:
+61 8 6375 2525
E:
admin@e25.com.au
W: element25.com.au
BUTCHERBIRD MANGANESE PROJECT
Mineral Resource Upgrade
In late October 2024, E25 announced an updated Mineral Resource Estimate (MRE) 6 for its 100%owned Butcherbird Manganese Project (Project) in the Pilbara region of Western Australia (WA). The
updated MRE delivered a 142% increase to the Measured and Indicated resource categories.
E25 completed an extensive infill drilling program at the Project in 2024, targeting known mineralisation
within the current granted Mining Lease M52/1074, where Butcherbird Stage 1 mining and processing
operations are located. Results from the infill drilling have been used to update the Mineral Resource
Estimate for the Yanneri Ridge, Coodamudji, Richies Find, and Mundawindi deposits 7.
The work program achieved the expected result, supporting a 142% increase to the (mining depleted)
2019 Measured and Indicated Resource base within the target mining area for Butcherbirdʼs planned
Stage 2 Expansion operations.
The updated MRE will support re-statement of the Butcherbird Ore Reserve, pending mine optimisation
and scheduling activities which are currently in progress, aiming to extend the current mine life.
The Butcherbird October 2024 Global MRE summary, (depleted for mining to December 2023), is shown
in Table 1, with details of each deposit shown in Table 2.
Table 1: Butcherbird Manganese Project - Global Mineral Resource Estimate - October 2024
Resource Category
Volume (m³)
Density (t/m³)
Tonnes (t)
Mn %
Measured
6,000,000
2.36
14,000,000
11.3
Indicated
50,000,000
2.33
116,000,000
10.1
Inferred
59,000,000
2.42
144,000,000
9.8
TOTAL
115,000,000
2.38
274,000,000
10.0
Table 2: October 2024 Butcherbird Global MRE by Resource Category and Deposit
Deposit
Resource
Category
Volume (m³)
Density (t/m³)
Tonnes (t)
Mn %
Measured
5,000,000
2.39
13,000,000
11.4
Indicated
38,000,000
2.33
89,000,000
10.1
Inferred
6,000,000
2.96
17,000,000
9.0
Subtotal
49,000,000
2.41
119,000,000
10.1
Measured
-
-
-
-
Indicated
11,000,000
2.36
27,000,000
10.2
Inferred
2,000,000
2.98
5,000,000
11.2
Subtotal
13,000,000
2.44
32,000,000
10.3
2024 Updated Mineral Resource Estimate
Yanneri Ridge
Coodamudgi
6
7
E25 ASX Announcement dated 29 October 2024
E25 ASX Announcement dated 27 August 2024
30 January 2025 | ASX: E25
2
Deposit
Mundawindi
Richies Find
2024 MRE
Sub Total
Resource
Category
Volume (m³)
Density (t/m³)
Tonnes (t)
Mn %
Measured
-
-
-
-
Indicated
-
-
-
-
Inferred
14,000,000
2.35
33,000,000
10.2
Subtotal
14,000,000
2.35
33,000,000
10.2
Measured
-
-
-
-
Indicated
-
-
-
-
Inferred
15,000,000
2.34
34,000,000
9.2
Subtotal
15,000,000
2.34
34,000,000
9.2
Measured
5,000,000
2.39
13,000,000
11.4
Indicated
50,000,000
2.34
116,000,000
10.1
Inferred
36,000,000
2.50
89,000,000
9.7
Subtotal
91,000,000
2.39
219,000,000
10.0
Previously Reported Mineral Resource Estimates
Ilgarrie Ridge
Inferred
15,000,000
2.35
36,000,000
9.9
Budgie Hill
Inferred
2,000,000
2.35
5,000,000
9.3
Bindi Bindi Hill
Inferred
6,000,000
2.35
14,000,000
10.4
Cadgies Flat
Inferred
100,000
2.35
300,000
10.0
Stockpiles
Measured
300,000
1.81
600,000
9.2
Measured
6,000,000
2.36
14,000,000
11.3
Indicated
50,000,000
2.33
116,000,000
10.1
Inferred
59,000,000
2.42
144,000,000
9.8
115,000,000
2.38
274,000,000
10.0
Butcherbird Global Mineral Resource Estimate
Total
Total
NOTE: MRE are reported above a 7% Mn economic cutoff with no top-cut. Mineral Resources are rounded to reflect they are an estimation,
numbers may not sum due to rounding. Mineral Resources are depleted for mining.
Full details of Butcherbird’s updated MRE can be found in the ASX Announcement dated 29 October
2024.
Mining Proposal and Mine Closure Plan Approved
Post quarter-end, in January 2025, E25 announced its planned expansion of Butcherbird had received
formal approval from the WA Department of Energy, Mines, Industry Regulation and Safety’s (DEMIRS)
Resource and Environmental Compliance Division 8. This is a key approval under the Western Australian
regulatory framework and marks an important milestone for the Butcherbird Project.
A Works Approval is the only pending approval required for Butcherbird to commence construction of the
expanded processing facility. E25 submitted its application for the Works Approval in October 2024, and
it is anticipated to be granted imminently, with no known impediments.
8
E25 ASX Announcement dated 13 January 2025.
30 January 2025 | ASX: E25
3
All other required approvals and access agreements are in place and established from Butcherbird’s
Stage 1 operations including water abstraction, heritage clearances, Native Title and pastoral
agreements.
Updated Ore Reserve Statement
Following the updated MRE, in January 2025, E25 announced a 107% increase in Ore Reserves at
Butcherbird, relating to the Yanneri Ridge and Coodamudgi manganese deposits within granted mining
lease M52/1074 9. These are two of the eight known deposits at Butcherbird.
Table 3: Butcherbird Ore Reserve Estimate 10
Tonnes
(Mt)
Grade
(Mn %)
Contained Mn
(Mt)
Proved
11.3
11.8
1.33
Probable
70.4
10.2
7.15
Proved
-
-
-
Probable
19.1
10.3
1.97
Proved
0.6
9.2
0.06
10.4
10.5
Deposit
Classification
Yanneri Ridge
Coodamudgi
Stockpiles
TOTAL
101.4
Element 25 updated the global Butcherbird MRE in October 2024 , which included a substantial
upgrade to the tonnages in the Measured and Indicated resource categories.
11
This updated Ore Reserve is developed from the October 2024 MRE for the Yanneri Ridge and
Coodamudgi manganese deposits. The resource models and their development are described
separately in the Mineral Resource Estimate report.
Proved and Probable Ore Reserves have been derived from Measured and Indicated Mineral Resources
in accordance with Joint Ore Reserve Committee (JORC) Code 2012 guidelines. The updated Ore
Reserve for the Project is summarised in Table 3.
The Ore Reserve classification reflects the Competent Persons’ assessment of the deposits with the
application of appropriate modifying factors.
More details can be found in the ASX Announcement dated 22 January 2025.
E25 ASX Announcement dated 22 January 2025.
Data are reported to significant figures to reflect appropriate precision in the estimate, and this may cause some apparent discrepancies in totals
11
E25 ASX Announcement dated 29 October 2024.
9
10
30 January 2025 | ASX: E25
4
Updated Expansion Feasibility Study
Further to the announcement of the updated Ore Reserve Statement, E25 announced it had completed
an updated Feasibility Study (Study or FS) 12, refining the previous FS released in January 2024 to
include an updated mining Reserve, updated operating costs and extended mine life at Butcherbird.
The updated FS utilises the forecast production data, along with a detailed review of the process flow
design to optimise the design of an expanded processing facility. Highlights of the updated FS included:
• The expansion will establish Butcherbird as a low-cost manganese operator (US$ 2.86/dmtu C1
cost) able to produce high-quality manganese concentrate at a globally competitive operating cost.
• The Feasibility Study utilises all the available measured and indicated resources within the 18.3year mine plan supporting this Study.
• The Measured, Indicated and Inferred Mineral Resources used to support the 18.3-year mine life
represents 68% of the total mineral resource inventory within the granted mining lease M52/1074.
• Low capital requirement of AU$64.8M capital in total construction costs including process and nonprocess infrastructure. Average base case annual operating cashflow of AU$70.5M at full
production.
• Forecast cashflows generate a simple payback period of 16 months from commencement of
operations.
• Expanded mining production and process commissioning is currently scheduled to commence
within 14 months from the final investment decision and securing project financing.
• Base case involves an annual production and sale of 1.1Mtpa of lump manganese ore grading
31.6% Mn.
• The concentrate production strategy complements and enhances E25’s plan to develop a highpurity manganese sulphate (HPMSM) plant in Louisiana to supply offtake partners General Motors
LLC (GM) and Stellantis NV (Stellantis) with HPMSM for electric vehicle (EV) battery cathodes13.
The Study contemplates a revised comminution and procession circuit based on learnings gained from
the operation of the current Butcherbird processing facility since 2021. Changes to the processing circuit
include the use of a mineral sizer for primary comminution, a dense media separation (DMS) drum for
final beneficiation and a tailings screen and thickener for tails thickening and improved water recovery.
12
13
E25 ASX Announcement dated 22 January 2025.
E25 ASX Announcements dated 9 January 2023 and 26 June 2023.
30 January 2025 | ASX: E25
5
A summary of the parameters used in this Study include:
• Increased manganese concentrate production to 1.1Mtpa.
• DMS process recovery of 83.7%.
• Overall processing plant recovery of 59.1%.
• Increased ore recovery and decreased ore loss due to change in processing equipment.
• Exchange rate (AUD:USD) of 0.67 in 2025, 0.68 in 2026, with a longer-term assumption of 0.69
from 2027 onwards.
• Capital cost estimate of AU$64.8M including:
•
Construction of an expanded processing infrastructure.
•
Construction of an expanded mining camp.
• A revised site organisation chart has been developed with updated costs reflective of the proposed
expansion.
• Updated mining costs based on the expanded mining requirements.
• Updated sustaining capex involving an expanded tails storage facility (TSF).
• Updated manganese ore pricing to reflect current forecasts.
The Study results confirm that the robust economics of the project are further improved, with the
economics and performance of the project benefiting from the inherent economies of scale achieved in
the larger-scale production operations. This results in better utilisation of mining and processing
equipment, improved operational efficiencies and better utilisation of the large resource/reserve base
underpinning the project.
More detail on the updated FS is available in the ASX announcement dated 22 January 2025.
HPMSM REFINERY PROJECT - LOUISIANA USA
DoE Awards US$166M (AU$268M) Grant to E25 HPMSM Project
In January 2025, E25 announced formal awarding and signing of a Grant Agreement for US$166 million
(AU$268 million) 14 in grant funding from the U.S. Department of Energy under the Battery Materials
Processing Grant Program, first announced in September 2024. This landmark funding will support the
construction of E25’s proposed battery-grade HPMSM facility in Louisiana, USA (Facility), which will
bring domestic production of a key critical battery raw material to the USA.
The grant award is in addition to the US$115 million (AU$185 million) already committed by offtake
partners GM and Stellantis.
The grant application was submitted under the DoE’s Battery Materials Processing Grant Program of the
Office of Manufacturing and Energy Supply Chains, which is funded by the Bipartisan Infrastructure Law.
The program is designed to provide grants for battery materials processing to ensure that the United
States has a viable battery materials processing industry. The grant forms a key component of E25’s
14
USD:AUD conversion rate 0.62. Reference: www.xe.com
30 January 2025 | ASX: E25
6
financing strategy for the Facility, and the project execution team will now work to finalise the project
implementation schedule.
The grant comprises a total of US$166,128,094 in grant funding, broken into five budget periods, each
relating to a staged phase of project execution. The structure of the grant is based on matching funding
(cost-share) being provided by the Company for a total of US$166,128,095 in cost-share. The grant
agreement outlines the tasks and milestones required for each budget period with associated reporting
and approval requirements.
Grant funding is made available during each budget period in accordance with the approved budget
items and the terms and conditions of the grant award. The budget periods, milestones and stage gates
have been agreed between the DoE contracts team and the Company as part of the grant negotiation
and award process subsequent to the announcement that the project had been selected for the grant
award 15.
Community Benefits Plan
The proposed Facility is supported by local communities, stakeholders, and the State of Louisiana, which
has approved a substantial incentives package to support the project 16, in acknowledgement of its
significant local benefits. The Company is committed to supporting the local economy during and after
the construction of the Facility, including a desire to recruit workers from the oil and gas industry and a
recently closed refinery that can potentially provide a skilled workforce to the Facility. The Company
intends to prioritise local workforce recruitment, including training programmes and engaging with local
suppliers. The project is expected to create 400 jobs during construction and 144 full-time ongoing roles
once production commences.
Project Financing Strategy
In 2023, E25 secured a US$85 million loan under an agreement with GM, whereby E25 will, in turn,
supply up to 32,500 metric tons of manganese sulphate annually for GM’s Ultium battery plant
requirements, which added to the commitments from Stellantis that include take-or-pay offtake
commitments for 45ktpa of HPMSM over five years and US$30 million of project funding 17. The two
transactions, combined with the grant award, total US$281M in financing support for the project, with
only minor additional funding now required to complete the project financing structure.
E25 has been co-ordinating a process to secure the balance of funding for the project’s construction
costs, which were estimated in the Company’s April 2023 Feasibility Study 18 at US$289 million.
About the E25 HPMSM Louisiana Project
Element 25 (Louisiana) LLC (Element 25 (Louisiana) or E25 LA) plans to build and operate a first-ofits-kind, environmentally sustainable refining facility in the Baton Rouge area, Louisiana, to produce
HPMSM, a critical raw material in lithium-ion batteries.
E25 ASX Announcements dated 9 January 2023 and 26 June 2023.
E25 ASX Announcement dated 19 December 2023.
17
E25 ASX Announcements dated 9 January 2023 and 26 June 2023.
18
E25 ASX Announcement dated 12 April 2023.
15
16
30 January 2025 | ASX: E25
7
E25 LA plans to construct a 230,000 square-foot (~21,000m2) HPMSM refining facility that will employ an
innovative process to produce approximately 71,650 tons (65,000 metric tonnes) of HPMSM annually
from the first processing train using manganese ore sourced from its Butcherbird manganese mine.
It will be one of the first commercial facilities to produce HPMSM in the U.S., reducing current
dependency on Chinese sources. The Facility will create hundreds of highly-skilled, construction and
permanent jobs for Louisianans. As outlined above, with the E25 Project Financing Strategy, E25 LA
has secured offtake and funding agreements, including five and seven-year supply agreements with
global automakers Stellantis and GM, and has now secured US$166M in grant funding from the US
Department of Energy.
E25 LA controls all intellectual property to develop and operate the HPMSM facility. It also has
developed a proprietary process to remove solid waste residue as byproducts, which each have
industrial applications, thus eliminating the need for a solid waste landform. E25’s efficient process
permits a mine-to-market carbon footprint that is approximately 67% lower than competitors in China 19.
The proposed site is located in the Baton Rouge area, and is proximal to raw materials suppliers,
abundant utilities, and infrastructure, including ports and roads, which also boosts the Project’s viability
and bolsters the local economy surrounding the facility. Project commissioning and development will be
supported by multiple U.S.-based companies, including those based in Louisiana.
CORPORATE
Acuity Capital
E25 announced that it has utilised its At-the-Market Subscription Agreement (ATM) with Acuity Capital
Investment Management Pty Ltd (Acuity Capital) 20 21 to raise AU$2,850,000 (inclusive of costs) by
agreeing to issue 8,700,000 fully paid ordinary E25.ASX shares to Acuity Capital at an issue price of
AU$0.3275 per share.
The 8,700,000 Element 25 shares will be issued as per the shareholder approval obtained at the
Company’s most recent Annual General Meeting on 22 November 2024 22. The issue price of $0.3275
represents a premium of 13% to the 5 trading day volume weighted average price (VWAP) of $0.2891 to
29 January 2025 (inclusive).
The funds raised will be put towards E25’s working capital.
Results of Annual General Meeting
At E25’s Annual General Meeting of Shareholders held on 22 November 2024, all resolutions put to the
meeting passed via a poll 23.
E25 ASX Announcement dated 21 February 2023.
E25 ASX Announcement dated 30 January 2025
21
E25 ASX Announcements dated 10 February 2023, 14 February 2023 and 16 June 2023
22
E25 ASX Announcement dated 22 November 2024.
23
E25 ASX Announcement dated 22 November 2024.
19
20
30 January 2025 | ASX: E25
8
ABOUT ELEMENT 25
Element 25 is an ASX-listed company (ASX: E25) that operates the world-class 100%-owned
Butcherbird Manganese Project in Western Australia and is currently undertaking activities to expand
production to approximately 1.1Mtpa of medium-grade high silica manganese ore for use in traditional
and new energy markets 24.
E25 is also commercialising innovative proprietary technology to produce battery-grade high-purity
manganese sulphate monohydrate (HPMSM) for use in Electric Vehicle (EV) battery manufacturing. The
Company is building its first HPMSM refinery in Louisiana USA to produce raw materials for the US EV
market, in partnership with General Motors LLC (GM) and Stellantis N.V. (Stellantis) 25. E25 aims to
become an industry leading, world class, low-carbon battery materials manufacturer.
The Louisiana refinery is planned as the first of several HPMSM facilities planned for development under
E25’s “Design One Build Many” commercialisation strategy which envisages a hub and spoke model,
with ore supplied from E25’s Butcherbird Mine in Western Australia to supply processing facilities in key
regional markets to supply HPMSM to the rapidly growing EV servicing key global regions.
Company information, ASX announcements, investor presentations, corporate videos, and other investor
material in the Company’s projects can be viewed at: www.element25.com.au.This announcement is
authorised for market release by Element 25 Limited’s Board of Directors.
Justin Brown
Media Inquiries:
Managing Director
Email: admin@e25.com.au
Phone: +61 (8) 6375 2525
Nathan Ryan
Email: nathan.ryan@nwrcommunications.com.au
Phone: +61 (0) 420 582 887
Competent Persons Statement
The Company confirms that in the case of estimates of Mineral Resource or Ore Reserves, all material assumptions and technical parameters
underpinning the estimates in the market announcements dated 29 October 2024 and 22 January 2025 continue to apply and have not
materially changed. The Company confirms that it is not aware of any new information or data that materially affects information included in
previous announcements, and all material assumptions and technical parameters underpinning the estimates continue to apply and have not
materially changed.
Investor Relations Disclaimer
Certain Statements included in this announcement are forward-looking statements concerning Element 25 Limited and its subsidiaries (E25)
and its operations, economic performance, financial condition, plans and expectations. Without limiting the foregoing, statements including the
words “believes”, “anticipates”, “plans”, “expects”, “could”, “potential”, “should” and similar expressions are also forward-looking statements.
All forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual
events or results to differ from those expressed or implied, including, without limitation, business integration risks; uncertainty of production,
development plans and cost estimates, commodity price fluctuations; political or economic instability and regulatory changes; currency
fluctuations, the state of the capital markets, uncertainty in the measurement of mineral reserves and resource estimates, E25’s ability to attract
and retain qualified personnel and management, potential labour unrest, reclamation and closure requirements for mineral properties;
unpredictable risks and hazards related to the development and operation of a mine or mineral or mineral deposit or mineral processing facility
that are beyond E25’s control, the availability of capital to fund all of the Company’s projects and other risks and uncertainties.
You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. E25 cannot assure you
that actual events, performance or results will be consistent with these forward-looking statements, and management’s assumptions may prove
to be incorrect. E25’s forward-looking statements reflect current expectations regarding future events and operating performance and speak
only as of the date hereof and E25 does not assume any obligation to update forward-looking statements if circumstances or management’s
beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place
undue reliance on forward-looking statements.
24
25
E25 ASX Announcement dated 23 January 2024.
E25 ASX Announcements dated 9 January 2023 and 26 June 2023.
30 January 2025 | ASX: E25
9
TENEMENT INFORMATION FOR QUARTERLY REPORT
31 December 2024
The mining tenements held at the end of the quarter and their location
Tenement
reference
Notes:
Location
Interest at
beginning of
quarter
Acquired/
Disposed
Interest at end of
quarter
E20/659
Eelya Hill WA
10%
N/A
10%
E52/1529
Mt Padbury WA
100% (Note 1)
N/A
100% (Note 1)
E52/2350
Butcher Bird WA
100%
N/A
100%
E52/3606
Yanneri Bore WA
100%
N/A
100%
E52/3706
Yanneri Pool WA
100%
N/A
100%
E52/3735
Limestone Bore WA
100%
N/A
100%
E52/3769
Kumarina WA
100%
N/A
100%
E52/3779
Beyondie Bluff WA
100%
N/A
100%
E52/3858
Yanneri Well WA
100%
N/A
100%
E52/4064
Neds Gap WA
100%
N/A
100%
E52/4149
Neds Gap WA
100%
N/A
100%
E52/4155
Weelarrana WA
100%
Disposed
0%
E52/4358
Butcherbird North WA
100%
N/A
100%
E52/4417
Weelarrana WA
0%
Acquired
100%
L52/211
Limestone Bore WA
100%
N/A
100%
L52/215
Butcherbird East 1 WA
100%
N/A
100%
L52/216
Butcherbird East 2 WA
100%
N/A
100%
L52/217
Butcherbird East 3 WA
100%
N/A
100%
L52/218
Butcherbird East 4 WA
100%
N/A
100%
L52/220
Butcherbird East 5 WA
100%
N/A
100%
L52/221
Butcherbird East 6 WA
100%
N/A
100%
L52/225
Butcherbird East 7 WA
100%
N/A
100%
L52/254
Butcherbird North WA
100%
N/A
100%
L52/255
Butcherbird North WA
100%
N/A
100%
L52/256
Butcherbird North WA
100%
N/A
100%
L52/257
Butcherbird North WA
100%
N/A
100%
L52/258
Butcherbird East WA
100%
N/A
100%
L52/269
Kumarina WA
0%
Acquired
100%
M52/1074
Yaneri Ridge WA
100%
N/A
100%
E57/1060
Victory Well WA
20%
N/A
20%
E63/2027
Lake Johnston WA
100%
N/A
100%
E63/2429
Lake Johnston WA
100%
N/A
100%
(1) 100% interest held in all minerals other than iron ore and manganese.
Table 4: Tenement Information for Quarterly Report to 31 December 2024
30 January 2025 | ASX: E25
10
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Element 25 Limited
ABN
Quarter ended (“current quarter”)
46 119 711 929
31 December 2024
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date
(6 months)
$A’000
26
184
(a) exploration & evaluation
0
(94)
(b) development
-
-
(c) production
(2)
(926)
(d) staff costs
(336)
(588)
(1,047)
(1,412)
-
-
(e) administration and corporate costs
1.3
Dividends received (see note 3)
1.4
Interest received
15
46
1.5
Interest and other costs of finance paid
(5)
(9)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other – Payment for HPMSM development
-
-
1.8
Other - Movement of cash previously
classified as non-restricted
-
-
1.9
Net cash from / (used in) operating
activities
(1,349)
(2,799)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
-
-
(443)
(443)
(1,927)
(4,106)
(d) exploration & evaluation
-
-
(e) investments
-
-
(a) entities
(b) tenements
(c) property, plant and equipment
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
(f)
Year to date
(6 months)
$A’000
-
-
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
(2,370)
(4,549)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
643
2.2
other non-current assets
Current quarter
$A’000
Proceeds from the disposal of:
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
(18)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (lease payments)
(97)
(194)
3.10
Net cash from / (used in) financing
activities
(97)
431
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
8,238
11,327
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(1,349)
(2,799)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(2,370)
(4,549)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
(97)
431
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
211
222
4.6
Cash and cash equivalents at end of
period
4,633
4,633
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
4,633
8,238
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
4,633*
8,238
*Excludes 30 January 2025 capital raising of $2,850,000 with Acuity Capital.
6.
Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
307
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-