ANNOUNCEMENT | 15 September 2026 | ASX: E25
ELEMENT 25 COMMENCES EARLY WORKS AT
BUTCHERBIRD EXPANSION PROJECT
HIGHLIGHTS
• Early site works have commenced at the Butcherbird Expansion Project in preparation for the
planned main construction phase.
• Works include site clearing, bulk earthworks and preparation of the planned process plant, run-of-
mine and non-process infrastructure as construction of process water storage pond and pipelines.
• Existing administration facilities will be relocated and new transportable offices and amenities
installed, together with supporting power, communications, potable-water and wastewater services.
• The programme will establish essential infrastructure and construction-ready areas for subsequent
processing plant construction and commissioning.
• Tender process for main CSMP and E&I work package is well advanced and contract award is
expected in line with the overall project plan.
Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to advise that early site
works have commenced at the Butcherbird Expansion Project (BBX) in preparation for process plant
construction and commissioning in accordance with the BBX project execution plan (PEP).
Element 25 Managing Director Justin Brown said “Commencement of the early works programme
marks tangible progress in executing our development plan for the Butcherbird Expansion Project.
The programme is focused on preparing the site and establishing the critical infrastructure required
for the main construction phase”.
Figure 1: Aerial overview of early works activities at the Butcherbird Project.
15 September 2026 | ASX: E25 2
WORK PACKAGER SCOPE SUMMARY
The early works programme (SP1) has been structured
to provide critical project infrastructure and establish
construction-ready areas for subsequent major
contracts associated with the construction of the BBX
processing plant and supporting facilities.
This work marks the transition of BBX into the
construction phase and underpins the Company’s
continued progress in advancing its strategy to expand
manganese production capacity and support E25’s
participation in the growing electric vehicle battery
materials supply chain.
The work package represents the first construction
phase of the project and is focused on establishing the site infrastructure and prepared work areas
required for the main plant construction program. The works are designed to de-risk project execution,
provide essential services, and ensure the site is construction-ready ahead of major processing plant
activities.
Scope of Early Works
Key activities include:
• Site clearing, grubbing and bulk earthworks to establish construction platforms for the expanded
processing plant, run-of-mine infrastructure and supporting facilities.
• Construction and commissioning of a new process water pond, including associated water
supply, pumping and pipeline infrastructure required to support construction and future
operations.
• Relocation and reinstatement of existing water services, including bore field pipeline connections
and standpipe facilities.
• Relocation of existing administration and support facilities and installation of new offices,
amenities and other non-process infrastructure.
• Installation of preliminary site services, including power, communications, potable water,
wastewater, roads and drainage infrastructure.
• Decommissioning and rehabilitation of the existing process water pond following successful
commissioning of the new facility.
Strategic Importance
The SP1 work programme establishes critical project infrastructure and construction-ready areas
necessary to support the subsequent development of the expanded 1.1Mtpa manganese concentrate
operation1
. Completion of these activities will enable the transition to the main construction phase and
support the planned recommencement of production at Butcherbird.
1
E25 ASX Announcement dated 22 January 2025
Figure 2: BBX Site Layout
15 September 2026 | ASX: E25 3
ABOUT ELEMENT 25
Element 25 is an ASX-listed company (ASX: E25) that operates the world-class 100%-owned
Butcherbird Manganese Project in Western Australia and is currently undertaking activities to
recommence production at approximately 1.1Mtpa of medium-grade high silica manganese ore2
for use
in traditional and new energy markets.
E25 is also commercialising innovative proprietary technology to produce battery-grade high-purity
manganese sulphate monohydrate (HPMSM) for use in Electric Vehicle (EV) battery manufacturing. The
Company is planning its first HPMSM refinery in Louisiana USA to produce raw material for the US EV
market, with support from leading global vehicle OEMs and a grant for US$166 million (A$268M) in
project funding from the U.S. Department of Energy (DoE) under the Battery Materials Processing Grant
(MESC) Programme3
.
An anticipated strategic shift towards lithium manganese rich (LMR) battery chemistries over high nickel
formulations will materially increase demand for HPMSM, with GM being one of the first automakers
looking to adopt this technology after spending more than a decade on research. Ford Motor Company
has also announced a plan to introduce LMR batteries to improve safety, energy density, and reduce
costs. LMR battery cells use around to 50-70% manganese increasing the required manganese by up to
10X compared to high nickel ternary chemistries.
Justin Brown Media Inquiries:
Managing Director
Email: admin@e25.com.au
Phone: +61 (8) 6375 2525
Nathan Ryan
Email: nathan.ryan@nwrcommunications.com.au
Phone: +61 (0) 420 582 887
Competent Persons Statement
The Company confirms that in the case of Production Targets, all material assumptions underpinning the production target, or the forecast
financial information derived from a production target, in the market announcement dated 22 January 2025 continue to apply and have not
material changed. All estimates or Mineral Resources or Ore Reserves underpinning the production target have been prepared by a competent
person or persons s in accordance with the requirements of the JORC Code, Appendix 5A.
The Company confirms that in the case of Mineral Resource or Ore Reserves, all material assumptions and technical parameters underpinning
the estimates in the market announcements dated 29 October 2024 and 22 January 2025 continue to apply and have not materially changed.
The Company confirms that it is not aware of any new information or data that materially affects information included in previous
announcements, and all material assumptions and technical parameters underpinning the estimates continue to apply and have not materially
changed.
Investor Relations Disclaimer
Certain Statements included in this announcement are forward-looking statements concerning Element 25 Limited and its subsidiaries (E25)
and its operations, economic performance, financial condition, plans and expectations. Without limiting the foregoing, statements including the
words “believes”, “anticipates”, “plans”, “expects”, “could”, “potential”, “should” and similar expressions are also forward-looking statements.
All forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual
events or results to differ from those expressed or implied, including, without limitation, business integration risks; uncertainty of production,
development plans and cost estimates, commodity price fluctuations; political or economic instability and regulatory changes; currency
fluctuations, the state of the capital markets, uncertainty in the measurement of mineral reserves and resource estimates, E25’s ability to attract
and retain qualified personnel and management, potential labour unrest, reclamation and closure requirements for mineral properties;
unpredictable risks and hazards related to the development and operation of a mine or mineral or mineral deposit or mineral processing facility
that are beyond E25’s control, the availability of capital to fund all of the Company’s projects and other risks and uncertainties.
You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. E25 cannot assure you
that actual events, performance or results will be consistent with these forward-looking statements, and management’s assumptions may prove
to be incorrect. E25’s forward-looking statements reflect current expectations regarding future events and operating performance and speak
only as of the date hereof and E25 does not assume any obligation to update forward-looking statements if circumstances or management’s
beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place
undue reliance on forward-looking statements.
2
E25 ASX Announcement dated 22 January 2025
3
E25 ASX Announcement dated 7 July 2026
Share your feedback
Discover